Posted: Wednesday, 03 July 2013 6:56AM

Bike Path



A project to upgrade and widen the Lake Park bike path was approved on a unanimous vote by the City Council Monday night.
                 
The Council awarded the contract for the to Dunn Blacktop Company.  The total cost will be almost $567,000.  But Assistant City Manager for Public Works, Keith Nelson said almost $200,000 was raised through local donations.

The changes are expected to include widening the path around both the east and west lake to10 feet and providing a smother surface.  Nelson said the project came in $50,000 under the estimated cost.
                  
The project is expected to get underway in August and be completed this fall.

Filed Under :  
People : Keith Nelson